Groupbridge Ltd completed the refurbishment of an existing bridge leading into the new nature reserve located on the Lion Hills estate, Soham, Cambridgeshire
As the main contractor Groupbridge Ltd liaised with the Environment Agency to agree the best approach to ensure protection to the watercourse. This lead to the installation of a temporary crash deck being installed underneath the existing bridge with a fully enclosed scaffold to capture any debris during grit blasting and painting of the existing steel beams
Once the steel structure had been refurbed the existing timber deck and handrails were removed and replaced with a new bespoke oak deck and handrails